Changing the project calendar / custom working times Part II
A friend of mine emailed me about a problem with changing the project calendar. To make a long story short I'll jump right to the point. He said that his Gantt chart is still showing Saturdays and Sundays displayed as nonworking (dotted gray background) even thaw he set them as working days in his project's calendar.
The answer is.... (There is a nice set of knifes for the lucky candidate :P ) … you have to change the Gantt charts nonworking time calendar. You have to right click on the Gantt chart and choose Nonworking times. After that you can change the calendar from Standard to your new project calendar.
Here is a screenshot of that menu:

Hope this helps,
L.