Drag & Drop feature in Gantt chart
Have you ever accidentally changed your project plan by using the drag & drop feature in Gantt chat? Well I have, and if I may say, it always takes me a lot of time to find out what the hell happened to my plan, and why did it go berserk.
Now, somebody might say something like "Hey Luka, you have a nice Show highlighting feature in 2007 version" and they would be 100% right. That feature automatically highlights all of the parts that were affected by you last "change". But still, I often have time spans on my projects when I don't change the plan, and I don't want the drag & drop feature activated because I have to use undo non-stop. I tried to find out if this feature is disableable... but to my misfortune it isn't.
So if any of you are wondering how to prevent Gantt chart drag & drop feature to change task duration, links... forget it, it isn't possible.